File #: ID 21-0355    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/27/2021 In control: City Council
On agenda: 6/15/2021 Final action: 6/15/2021
Title: Resolution Approving Bid in the Amount of $4,643,628.16 and Authorizing Execution of Contract 2019-006A with Jimmy R. Lynch & Sons, Inc. for the Reedy Fork Water Line Extension and Sewer Outfall Project
Attachments: 1. Lynch SoS.pdf, 2. MWBE Memo for Contract 2019-006A Reedy Fork Creek Water Line Extension.pdf, 3. 21-0355 RES Lynch.pdf
Title
Resolution Approving Bid in the Amount of $4,643,628.16 and Authorizing Execution of Contract 2019-006A with Jimmy R. Lynch & Sons, Inc. for the Reedy Fork Water Line Extension and Sewer Outfall Project

Body
Council Priority: Maintain Infrastructure and Provide Sustainable Growth Opportunities

Department: Engineering and Inspections
Council District: 2

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Mike Borchers, 373-2494
Contact 2 and Phone: Kenney McDowell, 373-2302

PURPOSE:
The bids for Contract 2019-006A, Reedy Fork Water Line Extension and Sewer Outfall Project, have been received. In order for the work to proceed on this contract, City Council approval is requested for award of the contract to Jimmy R. Lynch & Sons, Inc. for $4,643,628.16.

BACKGROUND:
The work in this contract generally consists of installation of 6,822 linear feet of 24-inch ductile iron sanitary sewer outfall line, by open cut, and bore and jack. Additionally, the work consists of the installation of approximately 6,249 linear feet of 24-inch DI water line and appurtenances with 5,349 feet installed by open cut, and 900 linear feet of 24-inch water line installed by directional drill, connecting to existing water lines near the intersections of Summit Avenue and Reedy Fork Parkway and Brown Summit Road and Chickasha Drive.

The bids were opened on May 6, 2021, and the apparent lowest, responsive bidder was Jimmy R. Lynch & Sons, Inc. with a bid of $4,643,628.16. The MWBE goals for this project are 8.0% MBE and 13.0% WBE. The contractor's commitments are 8.05% MBE and 13.52% WBE.

The other responsive bid received was:
Yates Construction Company, Inc. $5,094,442.04 MBE=8.0% WBE =13.0% Stokesdale, NC

Two other bids were received but they were not opened. One bid was deemed to be non-responsive because it was submitted improperly. The other bid was non-responsive because it did not meet MWBE goals nor Good Faith Efforts (GFE). An appea...