File #: ID 18-0024    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/4/2018 In control: City Council
On agenda: 2/20/2018 Final action: 2/20/2018
Title: Resolution Approving Bid in the Amount of $495,523.00 and Authorizing Execution of Contract 2017-72 with Shamrock Environmental for the Construction of the South Buffalo Water Quality & Habitat Improvements - Phase 4 Project.
Attachments: 1. sec of state.pdf, 2. 2017-072 South Buffalo Creek Phase IV - GFE Memo Letter-Shamrock.pdf, 3. 18-0024 resolution for 2017-72.pdf

Title
Resolution Approving Bid in the Amount of $495,523.00 and Authorizing Execution of Contract 2017-72 with Shamrock Environmental for the Construction of the South Buffalo Water Quality & Habitat Improvements - Phase 4 Project.

Body
Department: Engineering & Inspections
Council District: 1


Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Steve Drew 373-7893
Contact 2 and Phone: Kenney McDowell 373-2302

PURPOSE:
The bids for Contract 2017-72 - South Buffalo Water Quality & Habitat Improvements - Phase 4 project have been received. In order for the work to proceed on this contract, City Council approval is requested for award of the contract to Shamrock Environmental in the amount of $495,523.00.

BACKGROUND:
This work consists of all labor, equipment, and materials required for installation of stream restoration, enhancement, or stabilization work in and along 2,200 linear feet section of South Buffalo Creek. Includes the following: stream channel bank and flood plain grading, installation of bank stabilization practices, in-stream structure placement, removal and proper disposal of excess material from the project area at an appropriate approved disposal site, furnishing and planting live plant materials in-stream and throughout the floodplain, erosion control items, seeding and mulching, and tree removal.
The bids were opened on December 12, 2017. The MWBE participation goals were established at MBE=4% and WBE=3%.

Shamrock Environmental (Greensboro, NC) was evaluated and found to have met the goals with MBE=4.0% and WBE=7.6%.

Other bids received were:
River Works, Inc. $524,288.00 MBE=4.0%; WBE= 3.0% Raleigh, NC
KBS Earthwork $586,839.06 MBE= 4.3%; WBE= 6.1% Julian, NC
Carolina Environmental $604,524.80 MBE=5.1%; WBE=3.1% Pilot Mountain, NC
Wright Contracting $646,715.00 MBE=0.0%; WBE=9.2% Siler City, NC

The proposed date for start of construction is March 26, 2018. The proposed date of completion is July 4, 2018....

Click here for full text