File #: ID 17-0695    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/18/2017 In control: City Council
On agenda: 11/14/2017 Final action: 11/14/2017
Title: Resolution Approving Bid in the Amount of $11,427,643.04 and Authorizing Execution of Contract 2010-130A with D.H. Griffin Construction Company, LLC for Stewart Mill Force Main & Rock Creek Force Main Project
Attachments: 1. 2010-130A Stewart Mill Force Main and Rock Creek - GFE Memo Letter.pdf, 2. 17-0695 Resolution 2010-130A.pdf

Title
Resolution Approving Bid in the Amount of $11,427,643.04 and Authorizing Execution of Contract 2010-130A with D.H. Griffin Construction Company, LLC for Stewart Mill Force Main & Rock Creek Force Main Project

Body
Department: Engineering & Inspections
Council District: N/A

Public Hearing: N/A
Advertising Date/By: N/A

Contact1: Steven Drew 373-7893
Contact2: Kenney McDowell 373-2308

PURPOSE:
The bids for Contract 2010-130A - Stewart Mill Force Main & Rock Creek Force Main have been received. In order for the work to proceed on this contract, City Council approval is requested for award of the contract to D.H. Griffin Construction Company, LLC for $11,427,643.04.

BACKGROUND:
This work consists of installation of approximately 23,000 linear feet of 30-inch and 13,000 linear feet of 18-inch force mains. The bids were opened on October 5, 2017 and the apparent lowest, responsible bidder is D.H. Griffin Construction Company, LLC (Greensboro, NC) with a bid of $11,427,643.04.

The M/WBE utilization goal was MBE 3% and WBE 3%.
The contractor's commitment is MBE 3.4% and WBE 3.3%.

Additional bids received were:

Garney Companies $12,038,490.85 (MBE 3.1%; WBE 3.0%) Winter Garden, FL
State Utility Contractors $12,056,710.00 (MBE 0.3%, WBE 1.0%) Monroe, NC
Hall Contracting Corp. $12,195,082.00 (MBE 8.8%, WBE 3.1%) Charlotte, NC
Park Construction $12,688,324.35 (MBE 0.5%; WBE 2.3%) Morrisville, NC
Yates Construction $12,838,339.50 (MBE 11.4%, WBE 3.0%) Stokesdale, NC
English Construction $12,936,297.50 (MBE 0.0%, WBE 3.2%) Lynchburg, VA
J.R. Lynch & Sons $16,143,561.46 (MBE 3.0%, WBE 3.0%) Pilot Mountain, NC

The proposed date for start of construction is January 15, 2018. The proposed date of completion is April 10, 2019.

BUDGET IMPACT:
Funds for this $11,427,643.04 construction contract are budgeted in the following Water Resources Extension Fund accounts: 507-7012-01.6017 A13089 in the amount of $3,843,726.87 and 507-7012-02.6017 A13091 in the amount...

Click here for full text