File #: ID 21-0177    Version: 1 Name:
Type: Resolution Status: Passed
File created: 2/12/2021 In control: City Council
On agenda: 3/16/2021 Final action: 3/16/2021
Title: Resolution Approving Bid in the Amount of $2,298,856.62 and Authorizing Execution of Contract 2016-037A (TIP# B-5553) with Dane Construction, Inc. for the Ballinger Road Bridge Replacement Project
Attachments: 1. Dane SoS.pdf, 2. MWBE Memo - 2016-037A Ballinger Road Bridge.pdf, 3. 2016-037A Engineering DBE Review.pdf, 4. 2016-037A Garner-Murphy Prequalified DBE_WBE_HUB.pdf, 5. 21-0177 RES Dane Construction.pdf

 

Title

Resolution Approving Bid in the Amount of $2,298,856.62 and Authorizing Execution of Contract 2016-037A (TIP# B-5553) with Dane Construction, Inc. for the Ballinger Road Bridge Replacement Project

 

Body

 

Council Priority: Maintain Infrastructure and Provide Sustainable Growth Opportunities

 

Department: Engineering and Inspections

Council District: 5

 

Public Hearing: N/A

Advertising Date/By: N/A

 

Contact 1 and Phone: Hanna Cockburn, 373-4368

Contact 2 and Phone: Kenney McDowell, 373-2302

 

PURPOSE:

The bids for Contract 2016-037A, Ballinger Road Bridge Replacement, have been received.  In order for the work to proceed on this contract, City Council approval is requested for award of the contract to Dane Construction, Inc. for $2,298,856.62.

 

BACKGROUND:

This project includes federal/state funding and is subject to the U.S. Department of Transportation Disadvantaged Business Enterprise (DBE) program. The M/WBE Program Plan expressly states, “...the following categories of contracts shall be excluded from the scope and application of this Program Plan: (a) Contracts that are subject to the U.S. Department of Transportation Disadvantaged Business Enterprise Program and Airport Concessions Disadvantaged Business Enterprise Program as set forth in 49 CFR Parts 23 and 26 or any successor regulations or legislation.”

 

The DBE goal for this project is 8.00%.  Dane Construction, Inc. has committed to a DBE goal of 8.62%, and intends to use Garner-Murphy Construction, Inc. to fulfill this entire 8.62% contract commitment.  Garner-Murphy Construction, Inc. is located in Graham, NC, and is listed as a certified DBE firm with the North Carolina Department of Transportation.

 

The work consists of all labor, equipment, and materials required to remove and replace the existing bridge deck on Ballinger Road, as well as reconstruct approximately 1,400 feet of roadway.  The work will also include installing sidewalks and providing intersection improvements at the intersection of Ballinger Road and Wakefield Drive.

 

The bids were opened on February 4, 2021, and the apparent lowest, responsive bidder was Dane Construction, Inc. with a bid of $2,298,856.62.

 

The other responsive bids received were:

Fred Smith Company                                                               $2,410,410.00                                          DBE=8.02%                                          Raleigh, NC

Smith-Rowe, LLC                                                                  $2,434,793.79                                          DBE=8.02%                           Mt. Airy, NC

Yates Construction                                                                  $2,557,024.85                                          DBE=8.04%                         Stokesdale, NC

Zachry Construction                                                               $3,020,000.00                                          DBE=8.04%                                          Charlotte, NC

 

The proposed date for start of construction is May 2021.  The proposed date of completion is July 2022.

 

BUDGET IMPACT:

Funds in the amount of $2,298,856.62 are budgeted in three separate accounts:

 

$1,863,014.62     401-4562-01.6014 A19193  Ballinger Road Bridge Street Construction & Paving account

$249,044.00        503-7029-02.5615                Water Resources’ Sewer Lines account.

$186,798.00        503-7029-01.5615                 Water Resources’ Water Lines account

 

Budget adjustments are needed for the Sewer Lines and the Water Lines account.

 

RECOMMENDATION / ACTION REQUESTED:

It is recommended by the Departments of Engineering & Inspections, Transportation, and Water Resources that City Council approve the bid and award Contract 2016-037A (TIP# B-5553) for the Ballinger Road Bridge Replacement Project to Dane Construction, Inc. for the bid amount of $2,298,856.62.