File #: ID 20-0605    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/18/2020 In control: City Council
On agenda: 10/20/2020 Final action: 10/20/2020
Title: Resolution Authorizing Change Order #1, in the Amount of $37,500.00, for Contract 2018-0370 with WithersRavenel, Inc. for Additional Professional Design Services Needed for the E. Gate City Boulevard Roadway and Sidewalk Improvements Design
Attachments: 1. WithersRavenel_SoS.pdf, 2. MWBE Memo-CO1 Contract 2018-0370-E Gate City Blvd Roadway-Sidewalk Improv.pdf, 3. 20-0605 RES WithersRavenel.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
Resolution Authorizing Change Order #1, in the Amount of $37,500.00, for Contract 2018-0370 with WithersRavenel, Inc. for Additional Professional Design Services Needed for the E. Gate City Boulevard Roadway and Sidewalk Improvements Design

Body
Council Priority: Maintain Infrastructure and Provide Sustainable Growth Opportunities

Department: Engineering and Inspections
Council District: 1

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Kenney McDowell, 373-2302
Contact 2 and Phone: Jason Geary, 373-2302

PURPOSE:
City Council approval is requested for a change order to Contract 2018-0370 for the E. Gate City Boulevard Roadway and Sidewalk Improvements Design. This change order for $37,500.00 is to provide additional project coordination and water line designs that were not included in the original contract.

BACKGROUND:
This change order is necessary to provide additional professional services to the existing roadway and sidewalk design contract for E. Gate City Boulevard. As the design progressed, it was determined new water lines would be required at three different locations along the design corridor. A portion of this change order will be used to provide professional design services to incorporate these water lines into the final design for installation during construction.

Additional costs are also being included to provide public outreach and involvement to obtain public input on the project design. The proposed public involvement meetings will include a virtual public involvement meeting as well as an in-person meeting in order to obtain public input from all possible sources.

For the original contract amount, WithersRavenel, Inc. utilized a MBE firm in the amount of $26,110.00, or 9.00% of the total contract amount. For this change order, WithersRavenel, Inc. is proposing to utilize a WBE firm in the amount of $8,000.00, or 21.3% of the change order amount.

BUDGET IMPACT:
Funds for this change order will come from ...