File #: ID 20-0250    Version: 1 Name:
Type: Resolution Status: Passed
File created: 2/27/2020 In control: City Council
On agenda: 3/31/2020 Final action: 3/31/2020
Title: Resolution Approving Extension of Professional Services Contract 2018-051, in the Amount of $50,000.00, with Kimley-Horn and Associates, Inc. for Added Storm Drainage Tasks for the Davie Street Streetscape Project
Attachments: 1. SoS Kimley-Horn & Assoc.pdf, 2. MWBE Memo - Change Order 1 for Davie Street Streetcape Project.pdf, 3. 20-0250 RES Kimley-Horn & Assoc.pdf

 

Title

Resolution Approving Extension of Professional Services Contract 2018-051, in the Amount of $50,000.00, with Kimley-Horn and Associates, Inc. for Added Storm Drainage Tasks for the Davie Street Streetscape Project

 

Body

Council Priority: Maintain Infrastructure and Provide Sustainable Growth Opportunities

 

Department: Engineering & Inspections

Council District:  3

 

Public Hearing: N/A

Advertising Date/By: N/A

 

Contact 1 and Phone: Chris Spencer, 433-7218

Contact 2 and Phone: Kenney McDowell, 373-2302

 

PURPOSE:

Kimley-Horn and Associates, Inc. is needed to provide additional design engineering services for the Davie Street Streetscape Project.  City Council approval of a contract extension to the professional services contract in the amount of $50,000.00 is requested.

 

BACKGROUND:

The City of Greensboro desires to design construction plans from A. Brenner Place to McGee Street.  The design is to include: roadway and hydraulic engineering, landscape architecture, traffic engineering, and traffic signal analysis.  Also, included is the design for replacing an existing 12” CI water main with a new 12” DI water main.

 

Kimley-Horn and Associates, Inc. was awarded the design contract for the Davie Street Streetscape Project by City Council on October 16, 2018 in the amount of $604,863.00.

 

The Transportation Department has identified a need to add the following tasks: Subsurface Utility Engineering Level B (SUE B) to better identify all utility conflict and precisely quantify the conflicts and conflict resolution.  The cost to incorporate the additional engineering is $50,000.00.  With this extension, the new total amount of the contract will be 654,863.00.

 

The original MWBE utilization was WBE 15.3%. This additional design engineering service will utilize Wetherill Engineering, a WBE subcontractor.  

 

BUDGET IMPACT:

The design contract extension will be funded as follows:

 

484-2201-04.5410                     2016 Downtown Streetscape Improvements Bond                     $50,000.00

 

RECOMMENDATION / ACTION REQUESTED:

The Transportation and Engineering & Inspections Departments recommend approval of the contract extension with Kimley-Horn and Associates, Inc.