File #: ID 20-0020    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/13/2019 In control: City Council
On agenda: 2/18/2020 Final action: 2/18/2020
Title: Resolution Authorizing Change Order #2 in the Amount of $140,000.00 for Contract 2017-0430 with Yates Construction Company, Inc. for the Airport Lift Station and Sewer Line Project
Attachments: 1. Sec of State.pdf, 2. MWBE Memo 2017-043 Airport Lift Station.pdf, 3. 20-0020 RES Yates Construction.pdf

 

Title

Resolution Authorizing Change Order #2 in the Amount of $140,000.00 for Contract 2017-0430 with Yates Construction Company, Inc. for the Airport Lift Station and Sewer Line Project

 

Body

Council Priority: Maintain Infrastructure and Provide Sustainable Growth Opportunities

 

Department: Engineering & Inspections

Council District: 5

 

Public Hearing: N/A

Advertising Date/By: N/A

 

Contact 1 and Phone: Michael Borchers, 373-2494

Contact 2 and Phone: Kenney McDowell, 373-2302

 

PURPOSE:

City Council approval is requested for a change order to Contract 2017-0430 for the Airport Lift Station and Sewer Line Project.  In order to account for overruns in work due to procedural process changes (bore vs. open-cut for sewer line installation), approval is required for this change order, with Yates Construction Company, Inc., for $140,000.

 

BACKGROUND:

This work consists of all labor, equipment, and materials required for the abandonment of the existing lift station and installation of approximately 7,502 linear feet of 16-inch gravity sewer line, 789 linear feet of 8-inch ductile iron pipe sewer line, and 23 manholes.

 

The additional costs are due to the procedural process changes (bore vs. open-cut method for sewer line installation). The original contract amount is $4,983,020.  The approval of change order #1 was for $500,000.  With this change order amount of $140,000, this will make the new contract value $5,623,020.

 

The contractor’s MWBE participation for the construction phase services were MBE 0% and WBE 1.7%.  The MWBE office reviewed the contract and change orders for compliance and found that the WBE utilization will increase to 2.43%.

 

BUDGET IMPACT:

Funds in the amount of $140,000 for this change order are budgeted in the Water Resources Capital Improvement Fund account 503-7028-05.6019 A19050.  A budget adjustment is needed to use this account.

 

RECOMMENDATION / ACTION REQUESTED:

 

The Departments of Engineering & Inspections and Water Resources recommend that City Council approve this change order for $140,000 on contract 2017-0430 to Yates Construction Company, Inc. and the associated budget adjustment.