Title: Resolution Authorizing the Fieldcrest Road Widening from Patton Avenue to the End of Fieldcrest Road with Curb and Gutter on both Sides on Basis of Petition in the Estimated Amount of $530,000
Indexes: District 1
Attachments: 1. Vicinity Map, 2. Site Map, 3. Petition, 4. Notice of Proposed Improvements, 5. 19-0674 Fieldcrest Resolution

 

Title

Resolution Authorizing the Fieldcrest Road Widening from Patton Avenue to the End of Fieldcrest Road with Curb and Gutter on both Sides on Basis of Petition in the Estimated Amount of $530,000

 

Body

 

Council Priority: Maintain Infrastructure and Provide Sustainable Growth Opportunities

 

Department: Transportation

Council District: 1

 

Public Hearing: October 15, 2019

Advertising Date/By: September 5, 2019

 

Contact 1 and Phone: Chris Spencer, 433-7218

Contact 2 and Phone: William A. Kelly, 373-2320

 

PURPOSE:

City Council to consider widening and installing curb and gutter improvements along Fieldcrest Road on the basis of a Petition for Local Improvements.  City Council shall hold a Public Hearing to consider any property owners objections to the legality of authorizing the assessable roadway improvement project in compliance with City Charter Section 6.140.  City Council approval is requested in order for the work to proceed.

 

BACKGROUND:

Per City Charter Section 6.136 & 137 a petition requesting roadway improvements was signed by the majority of the assessable property owners who own a majority of the adjacent property frontage along the limits of the proposed Fieldcrest Road improvement.  The City Legal Department has verified the sufficiency of the petition and the project is being submitted to the City Council for its consideration.  A Notice of Public Hearing for Local Improvements was mailed to the last known property owners on August 29, 2019 and advertised on September 5, 2019, and a notice of a Public Hearing was published in the PeaceMaker for the Public Hearing to be conducted on September 17th.  At the September 17th meeting of Council, this item was postponed to the October 15th meeting of City Council without further advertising.

 

BUDGET IMPACT:

The estimated construction cost of this project is $530,000.  The properties will be assessed at $23.00 per front foot for the curb and gutter as allowed by City Charter Section 6.131.  The projected recovery through assessments levied against the adjoining properties is approximately $33,000.  Funding has not been established for this project.  The project will be considered for future funding through the City’s Capital Improvement Program (CIP) prioritization process and funding availability.

 

RECOMMENDATION / ACTION REQUESTED: