File #: ID 19-0526    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/22/2019 In control: City Council
On agenda: 8/20/2019 Final action: 8/20/2019
Title: Resolution Granting an Easement to Duke Energy Corporation for New Transformer and Underground Electric Service for the Glenwood Recreation Center
Attachments: 1. 07242019 Glenwood Easement map.pdf, 2. 19-0526 RES Glenwood-Easement.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
..Title
Resolution Granting an Easement to Duke Energy Corporation for New Transformer and Underground Electric Service for the Glenwood Recreation Center

Body

Department: Parks and Recreation
Council District: 1

Council Priority: Maintain Infrastructure and Provide Sustainable Growth Opportunities

Public Hearing:
Advertising Date/By:

Contact 1 and Phone: Nasha McCray, 433-7360
Contact 2 and Phone: Shawna Tillery, 373-7808

PURPOSE:
City Council approval is requested to convey a utility easement to Duke Energy to install new pad mounted transformer and new underground electrical power service between the Glenwood Recreation Center and the Coliseum Blvd Church of Christ.


BACKGROUND:
Glenwood Recreation Center has had parking flow issues for many years. To temporarily resolve this issue the Parks and Recreation Department has had a parking use agreement with the Coliseum Blvd Church of Christ since 2016. Due to parking constraints for the Glenwood Recreation Center, this agreement has allowed for overflow parking between both sites. Both sites have overall deteriorated parking conditions and traffic flow issues. Over the past year, the concept of a new traffic flow and expansion of parking lots has been jointly designed and approved by both parties. This project is being funded with 2016 Bond funds and will include a partial reimbursement from the Coliseum Blvd Church of Christ. The project will include 15 additional parking spaces, improved flow of traffic, and the removal of existing power lines to underground service for better connections between the parcels. The projected timeline for the project is to bid in August 2019 and contract selection by the fall of 2019.

For the new transformer and existing power lines to be placed underground, Duke Energy requires an easement to perform this work. Since the easement is an encumbrance on City property, City Council approval is required.


BUDGET IMPACT:
No funds are required, and there is no budge...