File #: ID 17-0808    Version: 1 Name:
Type: Ordinance Status: Passed
File created: 12/15/2017 In control: City Council
On agenda: 12/19/2017 Final action: 12/19/2017
Title: Ordinance in the Amount of $28,000,000 Appropriating Funds for Eugene Street Parking Deck Project
Attachments: 1. 17-0808 Eugene St Ordinance.pdf

 

Title

Ordinance in the Amount of $28,000,000 Appropriating Funds for Eugene Street Parking Deck Project

 

Body

Department: Transportation

Council District: 3

 

Public Hearing: NA

Advertising Date/By: NA

 

Contact 1 and Phone: Adam Fischer 336-373-2861

Contact 2 and Phone: Stephen Carter 336-333-6879

 

PURPOSE:

Subject to City Council approval of an agreement for the proposed downtown Eugene Street public parking deck, it is necessary to appropriate funds in the amount of $28 million for the project.

 

BACKGROUND:

On May 2, 2017, City Council approved a resolution authorizing the City Manager to enter into an agreement with CHI Greensboro, LLC, to design and build a downtown public parking deck, with the design cost of the parking structure not to exceed $2 million. A total of $2 million was appropriated in the Parking Facilities Bond Fund for design costs.

 

At this time, the City Council is requested to increase the project fund budget by $28 million to fund estimated construction costs.

 

BUDGET IMPACT:

Total project funding of $30 million for the parking deck will come from future bond proceeds. The City will advance funds to the project from existing reserves and will be reimbursed from the planned 2018 bond issue that funds the City’s share of the project. A budget amendment is required at this time to provide appropriations to fund estimated construction costs for the Eugene Street Parking Deck project in the Parking Facilities Bond Fund:

 

Current Project Budget                      $  2,000,000                                          

Recommended Amendment     28,000,000

                     Amended Budget                      $30,000,000

 

RECOMMENDATION / ACTION REQUESTED:

The Transportation Department recommends and requests approval of the attached budget ordinance appropriating funding in the amount of $28 million for construction of the Eugene Street downtown public parking structure.