File #: ID 17-0234    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/29/2017 In control: City Council
On agenda: 5/2/2017 Final action: 5/2/2017
Title: Resolution Approving Bid for $4,736,587.30 and Authorizing Execution of Contract 2009-004 (U-5326) with Triangle Grading & Paving, Inc. for the Construction of the W. Market Street at Guilford College Road Intersection Improvements Project.
Attachments: 1. sec of state.pdf, 2. 17-0234 RESOLUTION APPROVING BID AND AUTHORIZING EXECUTION OF CONTRACT 2009-004.pdf

Title
Resolution Approving Bid for $4,736,587.30 and Authorizing Execution of Contract 2009-004 (U-5326) with Triangle Grading & Paving, Inc. for the Construction of the W. Market Street at Guilford College Road Intersection Improvements Project.

Body
Department: Engineering & Inspections
Council District: 5

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Adam Fischer 373-2861
Contact 2 and Phone: Kenney McDowell 373-2302

PURPOSE:
The bids for Contract 2009-004 (U-5326) - West Market Street at Guilford College Road Intersection Improvements have been received. In order for the work to proceed on this contract, City Council approval is requested for award of the contract to Triangle Grading & Paving, Inc. in the amount of $4,736,587.30.

BACKGROUND:
This work consists of all labor, equipment, and materials required for installation of roadway improvements: unclassified excavation, storm drainage, asphalt paving, pavement markings, railroad crossing, retaining wall installation, and erosion control; along with ADA compliant concrete curb cuts and driveways.

The bids were opened on March 23, 2017 and the apparent lowest, responsible bidder is Triangle Grading & Paving, Inc. (Burlington, NC) with a bid of $4,736,587.30. This project is funded by 80% Federal and 20% State reimbursable funds and is subject to DBE requirements due to Federal guidelines.

The DBE utilization goal was 12.0%.
The contractor's commitment is DBE = 12.4%.

Other bids received were:

Sharpe Brothers $5,038,228.44 DBE=12.0% Greensboro, NC
Blythe Construction $5,848,187.50 DBE=18.2% Charlotte, NC
Yates Construction Co. $6,435,130.29 DBE=13.2% Stokesdale, NC


The proposed date for start of construction is May 22, 2017. The proposed date of completion is June 26, 2018.

BUDGET IMPACT:
Funds for this construction contract are budgeted in the following Street and Sidewalk Capital Project Fund account: 401-4547-01.6014 A16102.

RECOMMENDATION / ACTION REQUESTED...