File #: ID 17-0194    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/17/2017 In control: City Council
On agenda: 4/18/2017 Final action: 4/18/2017
Title: Resolution Approving Bid in the Amount of $2,204,999 and Authorizing Contract with AAR Roofing to Replace the Roof of the Greensboro Coliseum Special Events Center
Attachments: 1. Bid Tab - SEC Roof Replacement.pdf, 2. SEC Roof MWBE Memo.pdf, 3. 17-0194 Resolution SEC Roof Replacement.pdf
Title
Resolution Approving Bid in the Amount of $2,204,999 and Authorizing Contract with AAR Roofing to Replace the Roof of the Greensboro Coliseum Special Events Center

Body
Department: Coliseum
Council District: Citywide

Public Hearing: No
Advertising Date/By: No

Contact 1 and Phone: Colleen Vann, 373-7465
Contact 2 and Phone: Mike Perdue, 373-7457

PURPOSE:
City Council is requested to approve a contract with AAR Roofing to replace the roof for Greensboro Coliseum Special Events Center. The existing roof was installed in 1991 with a 25 year rubber membrane. This old roof will be replaced with a new 25 year rubber membrane roofing system. The contract with AAR Roofing will be in the amount of $2,204,999.

BACKGROUND:

At the April 5, 2016 City Council Meeting, City Council approved a $20,000,000 bond package that will be paid back with future hotel / motel tax revenues. These funds are to be used for Coliseum roof replacements for both the main Coliseum arena and Special Events Center, along with other Coliseum improvements, i.e. Fieldhouse building, new pool at the GAC, etc.

The Coliseum received three bids to replace the roof of the Special Events Center on Wednesday, April 11th, 2017. AAR Roofing submitted the lowest responsible base bid in the amount of $2,204,999. The total contract will be in the amount of $2,204,999 and the project duration is approximately 180 days.

The Goal Setting Committee determined that due to a lack of M/WBE availability in commercial roofing, no M/WBE goals should be set for this project. The selected vendor, however, has committed 5% of the contract to available MBE-certified firms.


The following is a list of contractors that submitted bids:

Contractor
City
Base Bid
AAR Roofing
Kernersville, NC
$2,204,999
Allied Roofing
Kernersville, NC
$2,234,985
Triad Roofing
Greensboro, NC
$2,299,133


BUDGET IMPACT:
This project is being funded from Hotel/Motel Tax revenues and thus does not have a negative impact to the Colise...