File #: ID 17-0055    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/13/2017 In control: City Council
On agenda: 2/7/2017 Final action: 2/7/2017
Title: Resolution Approving Bid and Authorizing Execution of Contract No. 2015-080A With S&S Building And Development for the Fire Station No. 63 Construction Project
Attachments: 1. Bid Tabs - General Single.pdf, 2. Fire Station 63 MWBE Memo.pdf, 3. 17-0055 Resolution

Title
Resolution Approving Bid and Authorizing Execution of Contract No. 2015-080A With S&S Building And Development for the Fire Station No. 63 Construction Project

Body
Department: Engineering & Inspections
Council District:

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Dwayne Church: 336-574-4013
Contact 2 and Phone: Butch Shumate: 336-412-5794

PURPOSE:
City Council is being requested to approve the bid received for the construction of Fire Station No. 63 and award the contract to S & S Building and Development.

BACKGROUND:
Fire Station 63 is a new station to be located at 4306 Burlington Road. This fire station will allow the department to serve approximately 4,231 citizens in accordance with established performance standards. The new Station is will be approximately 12,800 square feet with EMS and storage garage facility on site. The area identified for this project currently has a tax valuation in excess of $154,631,000.

The Facilities Construction division along with the Greensboro Fire Department has worked with TMA Architects to develop a design for the new station that will meet the needs of the Fire Department and the surrounding community. Bids for the project were received on September 29, 2016. The following is a tabulation of the bids received:

Base Bid (Total) M/WBE %
S&S Bldg and Dev. $4,596,000.00 1.4% (M) / 2.7 % (W)
Holden Building $4,890,000.00 3.8% (M) / 3.0% (W)
H.M. Kern Corp. $5,215,700.00 0% (M) / 0% (W)
KMD Construction no bid

The apparent low bidder was S&S Building and Development with a total bid in the amount of $4,596,000.00. The MWBE utilization goal was 10% MBE and 10% WBE. The contractor's commitment is 1.4% MBE and 2.7% WBE. A good faith investigation and review has been conducted, and it has been determined that the contractor made good faith efforts to comply with the City's MWBE policy (see Attachment B)...