File #: ID 16-0730    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/12/2016 In control: City Council
On agenda: 9/6/2016 Final action: 9/6/2016
Title: Resolution Authorizing Extension 3 of Contract 2012-095 with KRG Utility, Inc. for the Water and Sewer Rehabilitation Project "L" Project
Indexes: All Districts, WR Contracts
Attachments: 1. KRG Sec State.pdf, 2. MWBE Memo Water & Sewer Rehab Project L Extension 2016, 3. Agenda 160816 Project L Water Sewer Rehab Contract 2012-095 CO #5 Presentation.pdf, 4. 16-0730 Resolution 2012-095 Contract Extension 3.pdf

Title
Resolution Authorizing Extension 3 of Contract 2012-095 with KRG Utility, Inc. for the Water and Sewer Rehabilitation Project "L" Project

Body
Department: Water Resources
Council District: All

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Steven Drew, 373-7893
Contact 2 and Phone: Virginia Spillman, 373-3260

PURPOSE:
Water Resources wishes to exercise the option to extend Water and Sewer Rehabilitation Contract 2012-095 to add other various locations for pipe rehabilitation with funding approved in the FY 16-17 Budget. In order for work to proceed, approval for a contract extension is requested.

BACKGROUND:
Contract 2012-095 was approved by City Council on May 21, 2013. The contract was awarded to KRG Utility, Inc. The contract called for the rehabilitation of water and sewer lines by slip-lining, pipe bursting and cured-in-place pipe in various locations around the city. When this contract was bid, the City reserved the right to extend it as a "Unit Price Contract" on an annual basis, which is accounted for in the current adopted operating budget. Contract Extension 1 was approved by Council on 7/15/2014. Contract Extension 2 was approved by Council on 9/01/2015. Contract language provides the ability to increase unit prices up to 1.5% for each year of the extensions. To date, no increases have been proposed for the previous extensions. Water Resources proposed an increase of 1.5% for this extension due to increased labor and material costs.

Water Resources has identified additional water and sewer lines in the Westerwood and Lindley Park and Starmount neighborhoods, and throughout the City in support of the City's increased efforts on resurfacing. The majority of the lines in need of rehabilitation were installed prior to 1950 and have decayed over time resulting in increased incidents of maintenance, stoppages and repairs. The additional footage of 4-inch through 36-inch sewer lines to be cleaned, inspected by cam...

Click here for full text