File #: ID 16-0478    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/27/2016 In control: City Council
On agenda: 6/21/2016 Final action: 6/21/2016
Title: Resolution Authorizing Municipal Agreement with NC Department of Transportation for U-5842 - Elm-Pisgah Church Intersection Improvements Project
Attachments: 1. Municipal Agreement, 2. 16-0478 Resolution.pdf

Title
Resolution Authorizing Municipal Agreement with NC Department of Transportation for U-5842 - Elm-Pisgah Church Intersection Improvements Project

Body
Department: Transportation
Council District: 2 & 3

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Adam Fischer 336-373-2861
Contact 2 and Phone: Tyler Meyer 336-373-2254

PURPOSE:
A resolution needs to be approved to authorize municipal agreement with NC Department of Transportation for U-5842 - Elm-Pisgah Church Intersection Improvements Project.

BACKGROUND:
This project was identified by the Greensboro Transportation Department and was submitted by the MPO for funding through NCDOT's Prioritization 3 process and was included in the 2016-2025 State Transportation Improvement Program (STIP). NCDOT has agreed to administer the project phases (design, right-of-way & construction).

The project consists of dual left turns on Elm from the north and on Pisgah Church from the east, right turn lane on Elm from the south and on Pisgah Church from the east, medians on all four approaches to control driveway access, sidewalks, markings, and signal improvements. The project schedule per the STIP is to acquire right-of-way in 2017 and begin construction in 2018

Elm Street and Pisgah Church Road are City maintained streets, thus NCDOT is requiring the City to provide 20% of the project's costs. This initial agreement includes the design phase. NCDOT will be submitting amendments for the future right-of-way and construction phases when estimates per the construction plans are available.

BUDGET IMPACT:
A 20% local match of $20,000 from bond account 471-4503-01 (U-5842 Elm/Pisgah Church Intersection) will be sent to NCDOT following agreement being fully executed. A budget adjustment is required to move funds into the appropriate account.

RECOMMENDATION / ACTION REQUESTED:
The Transportation Department recommends and requests approval of the attached resolution and appro...