File #: ID 16-0342    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/15/2016 In control: City Council
On agenda: 5/17/2016 Final action: 5/17/2016
Title: Resolution Approving Extension of Professional Services Contract 2009-056A with Withers & Ravenel, Inc., for the Design of the Downtown Greenway Phase 2
Attachments: 1. Update on Downtown Greenway Council Presentation.pdf, 2. 16-0342 RES DTGW Phase 2 contract extension resoulution.pdf

Title
Resolution Approving Extension of Professional Services Contract 2009-056A with Withers & Ravenel, Inc., for the Design of the Downtown Greenway Phase 2

Body
Department: Engineering & Inspections
Council District: 2, 3

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Kenney McDowell, 373-2302
Contact 2 and Phone: Ted Kallam, 373-2302

PURPOSE:
Withers & Ravenel, Inc. is needed to provide additional engineering services for the federally funded Downtown Greenway Phase 2 project, EL5101DJ. City Council approval of a contract extension to the professional services contract in the amount of $130,997.75 is requested.

BACKGROUND:
The downtown greenway will enhance pedestrian and bicycle circulation in and around downtown, serving as a hub for a larger future greenway network and improving transportation safety and mobility choices. Phase 2 is the section of the greenway along Murrow Boulevard and Fisher Avenue, from E. Lee Street to N. Eugene Street.

Withers & Ravenel was awarded the design contract for Phase 2 by City Council on June 5, 2012, in the amount of $680,531. Two extensions to the contract for design services to upgrade water lines on a portion of W. Fisher Avenue and N. Church Street were authorized by Council on August 5, 2013, and August 3, 2015, in the total amount of $18,870.

The Transportation Department, with the approval of the NCDOT, has identified the need to add several items to the contract: a bike lane on Murrow Boulevard, bridge alterations at Summit Avenue, traffic signal design, revision of the ramp design at Summit Avenue, and a Phase II environmental site assessment. The cost to incorporate the additional engineering is $130,997.75. With this contract extension, the new total amount of the contract will be $830,398.75.

BUDGET IMPACT:
The design contract extension in the amount of $130,997.75 will be funded from Transportation Department account 401-4542-01.5410. A budget adjus...

Click here for full text