File #: ID 16-0311    Version: 1 Name: Clelarwell Construction Change Order
Type: Resolution Status: Passed
File created: 3/29/2016 In control: City Council
On agenda: 4/19/2016 Final action: 4/19/2016
Title: Resolution Authorizing Change Order No. 1 in the Amount of $750,200 to Contract No. 2011-062 with D. H. Griffin Infrastructure, LLC for the Mitchell Water Treatment Plant Clearwell Replacement Project
Indexes: District 3, WR Contracts
Attachments: 1. Sec State DH Griffin, 2. MWBE Clearwell Change Order 1, 3. 16-0311 Resolution Clearwell change order one

Title
Resolution Authorizing Change Order No. 1 in the Amount of $750,200 to Contract No. 2011-062 with D. H. Griffin Infrastructure, LLC for the Mitchell Water Treatment Plant Clearwell Replacement Project

Body
Department: Water Resources
Council District: 3

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Steven Drew, 373-7893
Contact 2 and Phone: Michael Borchers, 373-2494

PURPOSE:
Water Resources is requesting a contract change order to the Mitchell Water Treatment Plant Clearwell Replacement Contract 2011-062 to address a major failure to an existing 42-inch filter watermain, provide for rock removal and replacement of unsuitable soils. In order to repair the failure and address site conditions, approval for a contract change order is requested.

BACKGROUND:
The City Council awarded Contract 2011-062 for the construction of the Mitchell Water Treatment Plant Clearwell Replacement to D. H. Griffin Infrastructure, LLC in the amount of $5,604,000 on August 18, 2015. The work consists of: constructing a new 1 million gallon (MG) prestressed concrete clearwell tank, yard piping and appurtenances, grading, road and stormwater improvements, finished water piping and valve improvements in the high service pump station, and associated electrical and instrumentation work.

Change Order No. 1 is the result of conditions encountered by the Contractor during construction of the new clearwell and piping, including the discovery of a major leak on the 42-inch filter watermain. The 42-inch cast iron pipe that failed was installed in 1956 and carries treated water from the filter plant to the Lake Daniel finished water clearwell. Leaks from the cracks discovered in the pipe have significantly hampered clearwell foundation construction.

To allow the clearwell construction project to proceed the first 100 feet of line closest to and partially under the filter building will be repaired by means of a cured-in-place-pipe repair met...