File #: ID 16-0081    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/20/2016 In control: City Council
On agenda: 2/16/2016 Final action: 2/16/2016
Title: Resolution Approving Change Order in the Amount of $181,250.05 on the General Stormwater Improvements Contract 2014-19 with Yates Construction Company, Inc.
Indexes: District 2, District 3, District 4, WR Contracts
Attachments: 1. 2014-19 General Stormwater Improvements Change Order Memo.pdf, 2. 16-0081 Reso. 2014-19 Change Order.pdf

Title
Resolution Approving Change Order in the Amount of $181,250.05 on the General Stormwater Improvements Contract 2014-19 with Yates Construction Company, Inc.

Body
Department: Engineering and Inspections
Council District: 2, 3, 4

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Kenney McDowell - 336.373.4578
Contact 2 and Phone: Ted Partrick - 336.373.2308

PURPOSE:
City Council approval is requested for a change order to Contract 2014-19 for General Stormwater Improvements. In order to complete the work required under the contract, approval is required for this change order with Yates Construction, Inc., in the amount of $181,250.05.

BACKGROUND:
This work consists of stormwater infrastructure upgrades of existing drainage systems at three locations across the City of Greensboro. This project is part of the Water Resources Department's ongoing drainage system improvement program, which produces annual stormwater improvement construction contracts. The contract was awarded on March 17, 2015 to Yates Construction Company, Inc. (Stokesdale, NC) with a bid of $1,285,636.74. The MWBE contract commitment is MBE 3.2% and WBE 8.3%.

During construction, unforeseen site conditions and omissions within the contract documentation were discovered, which necessitated incurring additional contract expenses. The additional costs are due to the need to replace an unanticipated amount of soil in backfill in trenches, the need to redesign and move underground utilities and structures, and addressing the omission of miscellaneous items in the list of bid items.

The original contract amount is $1,285,636.74 and approval of this change order request in the amount of $181,250.05 will make the new contract value $1,466,886.79.

BUDGET IMPACT:
Funds for this construction contract and the changer order are budgeted in Stormwater Capital Improvements fund account 506-7015-01.6018 A16028.

RECOMMENDATION / ACTION REQUESTED:
The Depa...

Click here for full text