File #: ID 15-0748    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/25/2015 In control: City Council
On agenda: 9/15/2015 Final action: 9/15/2015
Title: Resolution Approving Bid in the Amount of $1,404,548.83 and Authorizing Execution of Contract 2010-026 (EL-5101DG) to Yates Construction Company for the General Sidewalk Improvements for Randleman Road and Florida Street.
Attachments: 1. Yates Construction.pdf, 2. 15-0748 Reso. Yates Construction.pdf

Title
Resolution Approving Bid in the Amount of $1,404,548.83 and Authorizing Execution of Contract 2010-026 (EL-5101DG) to Yates Construction Company for the General Sidewalk Improvements for Randleman Road and Florida Street.

Body

Department: Engineering & Inspections
Council District: |913|

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Adam Fischer - 373-2861
Contact 2 and Phone: Ted Partrick - 373-2308

PURPOSE:
The bids for Contract 2010-026 (General Sidewalk Improvements - Florida Street & Randleman Road (EL-5101 DG) have been received. In order for the work to proceed on this contract, City Council approval is requested for award of the contract to Yates Construction Company in the amount of $1,404,548.83.

BACKGROUND:
This work consists of all labor, equipment, and incidentals required for installing approximately 14,360 linear feet (2.7 Miles) of concrete sidewalks; along with ADA compliant concrete curb cuts, driveways, retaining walls, and safety rails.

The bids were opened on August 19, 2015 and the apparent lowest, responsible bidder is Yates Construction Company (Stokesdale, NC) with a bid of $1,404,548.83.

The DBE utilization goal was 7%.
The contractor's commitment is DBE = 9.0%.
Additional bid received:

Atlantic Contracting Co., Inc. $1,466,705.75 (DBE 7.4%) Greensboro, NC
Triangle Grading & Paving $1,558,459.32 (DBE 7.0%) Burlington, NC

The proposed date for start of construction is October 19, 2015. The proposed date of completion is June 25, 2015.

BUDGET IMPACT:
This project will be funded from 401-4545-01.6015 A11089. A budget adjustment is required to move funding from the right of way (ROW) account into the construction account. As ROW is not a grant eligible expense, all of the ROW budget will be transferred to construction.

RECOMMENDATION / ACTION REQUESTED:
It is recommended and requested by the Departments of Engineering & Inspections and Transportati...