Title: Resolution Approving Bid in the Amount of $333,106 and Authorizing Execution of Contract with Wayne Brothers, Inc. for the Transfer Station Tipping Floor Repairs project
Attachments: 1. Bid Tab2-General Single.pdf, 2. 20150518 PAW-JWilliams Transfer Station Floor Repair Recommendation.pdf, 3. WayneBros-SecOfState.pdf, 4. 15-0441 Reso. Wayne Bros..pdf
Title
Resolution Approving Bid in the Amount of $333,106 and Authorizing Execution of Contract with Wayne Brothers, Inc. for the Transfer Station Tipping Floor Repairs project

Body
Department: Field Operations
Council District: 5

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Chris Marriott 373-7612
Contact 2 and Phone: Butch Shumate 412-5794

PURPOSE:
City Council is being requested to approve the bid received for the repair of the Solid Waste Transfer Station Tipping Floor and award the contract to Wayne Brothers, Inc.

BACKGROUND:
The Transfer Station is responsible for the transfer of municipal solid waste which is transported and disposed of at the Uwharrie Regional Landfill. The Transfer Station has been operational since September 2006 and can process up to 1,200 tons of waste per day. Municipal solid waste at the transfer station is deposited onto a concrete floor prior then placed into tractor trailers located beneath the facility. Routine activities associated with the transferring of waste destroy the integrity of the floor over time which will require full replacement of the solid waste tipping floor on a regular basis. Though the actual frequency of replacement will be based on the volume and type of waste processed through the facility and the resulting damages, the replacement interval is estimated to be every 7 years.

The Facilities Construction Division along with the Field Operations Department has worked with HDR, Inc. (Engineers) to develop and design repair details for the existing concrete slab tipping floor. Bids for the project were received on May 15, 2015. The following is a tabulation of the bids received:

Base Bid
Wayne Brothers, Inc. $333,106.00
Laughlin-Sutton Constr. Co. $694,064.00

The apparent low bidder was Wayne Brothers, Inc with a total bid in the amount of $333,106.00. The MWBE Goal Setting Committee considered this project on April 2, 2015. The Committ...