File #: ID 15-0029    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/15/2014 In control: City Council
On agenda: 1/6/2015 Final action: 1/6/2015
Title: Resolution Approving Bid in the Amount of $961,000.00 and Authorizing Execution of Contract No. 2012-066 with Bar Construction Company, Inc. for the Jaycee Park Parking and Stormwater Improvements Project
Indexes: District 3, WR Contracts
Attachments: 1. Bar Construction Company.pdf, 2. Jaycee Park SW Improvements Map.pdf, 3. 15-0029 Reso. Jaycee Park Bar Const..pdf

Title
Resolution Approving Bid in the Amount of $961,000.00 and Authorizing Execution of Contract No. 2012-066 with Bar Construction Company, Inc. for the Jaycee Park Parking and Stormwater Improvements Project

Body
Department: Water Resources
Council District: 3

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Steve Drew - 336.373.7893
Contact 2 and Phone: Ted Partrick - 336.373.2308

PURPOSE:
Bids have been received for the Jaycee Park Parking and Stormwater Improvements (Contract 2012-066). City Council approval of an award to Bar Construction Company, Inc. in the amount of $961,000.00 is requested.

BACKGROUND:
This contract consists of parking lot improvements to capture and treat stormwater runoff from the parking lot. Improvements include constructing a biocell, tree boxes, and pervious parking spaces to capture and filter runoff of the parking lot.

The contract was advertised in August and the bids opened on September 23, 2014, but the bids were not responsive to the MWBE instructions. The contract was re-advertised in October with bid opening on November 25, 2014. One responsive bid was received. Because this was the second advertisement and bid opening, award of this construction contract with only one bidder complies with Charter Section 4.113. The bidder was Bar Construction Company, Inc. (Greensboro, NC) with a bid of $961,000.00.

The MWBE goals were MBE=5% and WBE=5%. The contractor met the goals at: MBE=5% and WBE=7%.

The anticipated date for start of construction is February 9, 2015 with anticipated completion by June 9, 2015.

BUDGET IMPACT:
Funding is budgeted in the Water Resources Stormwater Capital Project Fund account 506-7014-04.6018 A15045. A budget adjustment is needed to use this account.

RECOMMENDATION / ACTION REQUESTED:
The Engineering & Inspections and Water Resources Departments recommend approval and award of the Jaycee Park Parking and Stormwater Improvements to Bar ...

Click here for full text