PURPOSE:
City Council approval of the prime contractor prequalification process and selection results for the T. Z. Osborne Water Reclamation Facility 56 MGD Upgrade Package II Construction Contract (2011-038A) is requested as required by Session Law 2014-42.
BACKGROUND:
In accordance with the overall plan by Water Resources Department to complete necessary upgrades at the T.Z. Osborne Water Reclamation Facility the second of three associated construction contracts is ready for bidding. As part of the bidding process for package II the Department made a decision to prequalify prime contractors due to the magnitude, complexity, and potential cost tied to the construction activities associated with package II treatment upgrades. Package two will upgrade the treatment capacity at T.Z. Osborne through primary treatment hydraulic improvements, the replacement of two existing blowers for process aeration and the modification of existing fine bubble diffusers in the aeration basins. The addition of 3 new secondary clarifiers, repairs to the existing return activated sludge and waste activated sludge systems and standby power generation improvements will occur as well.
Session Law 2014-42 was approved on June 30, 2014 and applies to construction or repair contracts awarded after October 1, 2014. The new law stipulates a governmental entity may prequalify bidders for a particular construction or repair work project when certain requirements are met. The requirements include utilization of one of the construction methods authorized in G.S. 143-128(a1)(1) through G.S. 143-128(a1)(3)...