Skip to main content
File #: ID 14-0578    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/28/2014 In control: City Council
On agenda: 9/16/2014 Final action: 9/16/2014
Title: Resolution Approving the Bid in the Amount of $2,462,000 and Authorizing Execution of Contract 2013-079 With Wharton-Smith, Inc. for the Mitchell Sediment Basin Building Structural Improvements and Filter Plant HVAC Improvements
Attachments: 1. SOS Wharton-Smith Inc.pdf, 2. MWBE Mitchell Filter Plant Improvements PH I .pdf, 3. 14-0578 Ressolution Mitchel Sediment - Wharton-Smith, Inc..pdf

Title
Resolution Approving the Bid in the Amount of $2,462,000 and Authorizing Execution of Contract 2013-079 With Wharton-Smith, Inc. for the Mitchell Sediment Basin Building Structural Improvements and Filter Plant HVAC Improvements

Body
Department: Engineering & Inspections
Council District: 3

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Mike Borchers - 373-2494
Contact 2 and Phone: Ted Partrick - 373-2308

PURPOSE:
The bids for Contract 2013-079 (Mitchell Sediment Basin Building Structural Improvements/Mitchell Filter Plant HVAC Improvements) have been received. In order for the work to proceed on this contract, City Council approval is requested for award of the contract to Wharton-Smith, Inc. in the amount of $2,462,000.00.

BACKGROUND:
This work consists of all labor, equipment, and incidentals required for structural, HVAC, process chemical feed systems, piping, and demolition improvements at the Mitchell Water Treatment Plant. The proposed date for start of construction is October 20, 2014. The proposed date of completion is July 17, 2015.

The bids were opened on July 24, 2014 and the apparent lowest, responsible bidder is Wharton-Smith, Inc. (Lake Monroe, Florida) with a bid of $2,462,000.00.

The M/WBE utilization goal MBE 10% and WBE 12%. Upon completion of a Good Faith investigation and review by the M/WBE Office a determination was made that the company met the WEB goal and demonstrated adequate Good Faith Efforts to try to meet the MBE goal. The actual MBE goal commitment was decreased from 10.6% to 0% because of the proposed MBE firm (CITI located in Mecklenburg County) did not meet the Significant Business Presence requirement in the M/WBE Program Plan. The final contract commitment is MBE 6.5% and WBE 16.0%.

Additional bid received:

Laughlin-Sutton Construction Co. $2,749,000.00 (MBE 1.5%, WBE 16.0%) Greensboro, NC


BUDGET IMPACT:
Funds for this construction contract are budgete...