Bids have been received for the Resurfacing of Streets (Contract 2013-001). City Council approval of an award to Blythe Construction, Inc. in the amount of $2,209,955.00 is requested.
BACKGROUND:
This contract consists of resurfacing approximately 11.3 miles of streets. It will include approximately 14,772 tons of asphalt pavement overlay, along with asphalt milling and minor utility adjustments. The bids were opened on February 20, 2014 and the apparent lowest, responsible bidder was Blythe Construction, Inc. (Charlotte, NC) with a bid of $2,209,955.00.
The Resurfacing Contract 2013-001 had subcontracting goals set at 3% for Minority and 3% for Women firms. At the April 1, 2014 City Council meeting, staff was asked to review the goals. Upon further review the goals were amended to 6% for Minority and 5% for Women owned firms. The general contractor with the lowest responsible bid, Blythe Construction, has agreed to meet the new goals.
The work to be provided under this contract includes the following items at these estimated costs.
General Conditions (insurance, mobilization, permits, contingency, etc.) $270,000
Milling (removal of top surface of existing pavement) $201,560
Concrete ramps and sidewalks for ADA upgrades $28,725
Adjusting manholes and valves to new road grades $315,000
Hauling (millings and asphalt) $25,000
Paving (less hauling, includes asphalt, paving and patching) $1,967,743
The new goals of 6% and 5% reflect both the amount of work in concrete, adjustments to manholes and valves, and hauling, and the number of available certified firms...