File #: ID 14-0327    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/21/2014 In control: City Council
On agenda: 6/3/2014 Final action: 6/3/2014
Title: Resolution Approving Extension of Professional Services Contract 2005-009 with US Infrastructure, Inc. for the Thoroughfare Sidewalks Project
Attachments: 1. US Infrastructure SOS, 2. Resolution, 3. GDOT Agenda 140603 IFYI memo Design Contract Extension USInfrastructure Sidewalks.pdf

Title
Resolution Approving Extension of Professional Services Contract 2005-009 with US Infrastructure, Inc. for the Thoroughfare Sidewalks Project

Body
Department: Engineering & Inspections
Council District: All

Public Hearing: N/A
Advertising Date/By: N/A

Contact 1 and Phone: Ted Partrick, 373 2308
Contact 2 and Phone: Adam Fischer, 373-2861

PURPOSE:
US Infrastructure, Inc., is being requested to provide additional engineering design services during the construction phases of various sidewalk projects they designed for the 2005 Thoroughfare Sidewalks Design project. City Council approval of a change order to the professional services contract with US Infrastructure in the amount of $21,890.00 is requested.

BACKGROUND:
US Infrastructure, Inc., is being requested to provide additional engineering design services during the construction phases of various sidewalk projects they designed for the 2005 Thoroughfare Sidewalks Design project. City Council approval of a change order to the professional services contract with US Infrastructure in the amount of $21,890.00 is requested.

BACKGROUND:
On January 14, 2005, City Council approved award of a design contract to US Infrastructure, Inc., for $545,812. US Infrastructure has an engineering design office in Greensboro. The design of the original projects, with the addition of the Bessemer Avenue project, was completed by October 2006. Four change orders to the original contract have been approved. The current contract total including the four change orders is $687,094. The new total contract amount will be $708,984.
This design contract is for the construction of 13 sidewalk projects with a total of 78,600 feet (14.9 miles) of sidewalks along Bessemer Avenue, Cornwallis Drive, Cone Boulevard, Florida Street, O'Conner Street, Lawndale Avenue, Market Street, Vandalia Road, and Wendover Avenue.
Change Order #5 is necessary to fund the remaining work on the contract. Nine of the eleven proj...